Days to Completion (for Budget) Calculator
Days = remaining budget / daily burn rate. Works backward from spend to project schedule.
Result
Loading calculator…
—
How to use this calculator
- Enter budget remaining (not total — what's left).
- Estimate true daily burn from last 2 weeks of invoices.
- Pick crew's actual workdays per week.
- Compare workdays of runway to scope remaining.
About this calculator
When a project is mid-flight and overrunning, the question shifts from "what does it cost?" to "how long can we keep going?" Daily burn rate (labor + materials per active workday) divided into remaining budget gives a hard runway. Use this to decide whether to push through, pause for a fresh draw, or trim scope. Be honest about the burn rate — include subcontractor invoices arriving 30 days late, equipment rental, and any owner-paid materials. Runway shorter than the remaining scope = a hard conversation incoming.
Frequently asked
How do I figure my real burn rate?+
Last 14 calendar days: total spent / number of workdays in that window. Don't use early-project burn — it under-estimates.
Why workdays vs. calendar days?+
Crews don't work weekends or holidays. Burn happens on workdays. Calendar days follow from workdays divided by work week.
What if the runway is too short?+
Three options: (1) increase budget — additional draw, second loan, owner cash; (2) reduce scope — defer items; (3) reduce burn — fewer trades on site simultaneously.
How does weather factor in?+
It doesn't reduce burn (you still pay supervisor + minimum crew) but it stretches calendar days. Add 10-20% calendar buffer for outdoor work.
Better metric than days?+
Earned-value: % complete × budget vs. spent so far. But days-of-runway is the visceral check — "am I going to hit a wall?"
Related calculators
Project Cash Flow Calculator
Monthly cash flow = inflows (loan draws, owner contributions) − outflows (labor, materials) over project duration.
Project Contingency Calculator
Safe budget = base × (1 + contingency %). New construction 5%, remodels 10-15%, gut renos 20%+.
Change Order Cost Impact Calculator
Revised total = base contract + change orders + contingency. Track scope creep against budget.
Contractor Payment Schedule Calculator
Distribute total contract across milestones (deposit / start / mid / completion) by % allocation.
Construction Loan Payment Calculator
Construction loan: interest-only on disbursed balance during build, then converts to permanent mortgage.
Equipment Rental Cost Calculator
Rental cost = best of (daily × days) vs. (weekly × weeks) vs. (monthly × months) — picks the cheapest tier.