Change Order Cost Impact Calculator

Revised total = base contract + change orders + contingency. Track scope creep against budget.

Inputs

Result

Revised total to date
$58,000
⚠️ $3,000 over base+contingency.
  • Base contract$50,000
  • Change orders12.0% of base$6,000
  • Contingency budget10% of base$5,000
  • Contingency used$2,000
  • Contingency remaining$3,000
  • Contingency overage$0
  • Baseline (base+cont)$55,000
  • Revised total$58,000

Step-by-step

  1. Contingency budget = base × 10% = $5,000.
  2. Revised = base + change orders + contingency used = $58,000.
  3. Over baseline by $3,000 — reset expectations or trim scope.

How to use this calculator

  • Enter the original signed contract.
  • Sum up all approved change orders.
  • Enter contingency budget set aside upfront.
  • Track cumulative contingency used as work progresses.

About this calculator

Change orders are nearly inevitable on remodels — discovered conditions, scope additions, fixture upgrades. The industry rule of thumb is 3-5% of base for new construction, 8-15% for remodels, 15-25% for older-home restorations. Track each change order separately with: cost, time impact, and signed approval. A "small" change order that adds 5 days × $1,000/day overhead is often the real budget killer, not the visible material cost.

Frequently asked

Yes — verbal "while you're in there" requests cause the most disputes. No work without signed change order.

Related calculators