Subcontractor Payment Schedule

Milestone-based payment schedule between GC and subcontractor — phase, deliverable, amount, target date, retainage, status, lien-waiver requirement.

Customise

Typical 5-10%. Released after final + lien waivers.

Live preview

SUBCONTRACTOR PAYMENT SCHEDULE  (Milestone-Based Draw Schedule)

═══════════════════════════════════════════════════════════════════════════

Project:               Maple Ridge Townhomes — electrical scope
Address:               1842 Maple Ridge Lane, Hillsboro, OR 97124
General contractor:    Cascade Build LLC
Subcontractor:         NW Electric & Power Inc.
Trade / scope:         Residential electrical: rough-in, service panel install, device trim-out, final inspection coordination
Subcontract date:      April 15, 2026
Subcontract value:     $48,500.00
Retainage per draw:    10%
Payment terms:         Net 7 days after GC receives the corresponding Owner draw (pay-when-paid timing).

═══════════════════════════════════════════════════════════════════════════

MILESTONES

   #  | Phase            | Deliverable                                  | Amount       | Retain       | Net          | Target      | Status
  ----|------------------|----------------------------------------------|--------------|--------------|--------------|-------------|--------
    1 | Mobilization     | Materials on site + permit pulled            |    $4,850.00 |      $485.00 |    $4,365.00 | 2026-04-22  | DUE   
    2 | Rough-in         | All rough-in wiring + service entrance ready |   $19,400.00 |    $1,940.00 |   $17,460.00 | 2026-05-08  | DUE   
    3 | Inspection pass  | County rough-in inspection approved          |    $4,850.00 |      $485.00 |    $4,365.00 | 2026-05-15  | DUE   
    4 | Trim-out         | Devices installed, panel labeled, GFCI/AFCI  |   $14,550.00 |    $1,455.00 |   $13,095.00 | 2026-05-29  | DUE   
    5 | Final            | Final inspection + as-built drawings + warra |    $4,850.00 |      $485.00 |    $4,365.00 | 2026-06-12  | DUE   

  TOTAL                                                                  $48,500.00    $4,850.00   $43,650.00

Milestone total reconciles with subcontract value.

═══════════════════════════════════════════════════════════════════════════

LIEN-WAIVER REQUIREMENT
Each progress payment: CONDITIONAL waiver upon progress payment (state statutory form). Final payment: UNCONDITIONAL waiver upon final payment (state statutory form). GC may withhold any payment until the conditional waiver for the PRIOR payment has been received. Subcontractor warrants no unpaid lower-tier subs or material suppliers as of each waiver date.

CHANGE-ORDER POLICY
No additional work outside the schedule above without a written change order signed by GC. Verbal authorizations are at the Subcontractor's risk. Change orders amend this schedule with new milestone + amount + date; an updated schedule is re-issued upon execution.

NOTES / STATE-SPECIFIC PROMPT-PAY
Prompt-payment statute: project is in Oregon — ORS 701.625 + 701.420 (private + public prompt-pay acts) apply. GC must release payment to Subcontractor within 7 days of receipt of Owner draw on the corresponding milestone, less retainage. Disputed amounts may be withheld, but undisputed amounts must flow. Interest on late payments accrues per state-statutory rate.

═══════════════════════════════════════════════════════════════════════════

SIGNATURES

GC:   _________________________     Date: _____________
      Cascade Build LLC

Sub:  _________________________     Date: _____________
      NW Electric & Power Inc.

About this template

A subcontractor payment schedule turns the sub's lump-sum contract value into a milestone-based draw schedule that is enforceable by state prompt-payment statutes. **Three structural choices** drive cash-flow risk: (1) **Retainage** — typically 5-10% withheld per draw, released after final + lien waivers; state statutes (CA Pub. Cont. Code §7107, FL Stat. §218.735, TX Prop. Code §53.107) limit how much and how long. (2) **Pay-when-paid vs. pay-if-paid** — these are different clauses. *Pay-when-paid* is a timing clause: the sub gets paid AFTER the GC gets paid, but if the Owner never pays, the sub still gets paid eventually. *Pay-if-paid* shifts the Owner-credit risk to the sub: if the Owner never pays, the sub never gets paid. Pay-if-paid is UNENFORCEABLE in NY (Lien Law §34), NC (Wachovia Bank, NA v. Smithfield Foods), CA public projects, and limited in WI / IL / SC. (3) **Lien waivers** — conditional (upon progress payment) at each draw, unconditional (upon final payment) at close-out, in the state's statutory form when one exists (CA, AZ, FL, GA, MS, MO, NV, TX, UT, WY have statutory forms). **State prompt-payment acts** set the maximum window for the GC to flow payment to the sub after receiving the Owner draw — typically 7-10 days for the GC-to-sub leg. Late payment accrues statutory interest (1-1.5%/month is common). **Milestone definition matters**: vague "rough-in complete" leads to disputes; cite the specific code section being inspected (e.g. "county rough-in inspection passed per IRC E3406") so the trigger is objective. **Change orders** must amend the schedule explicitly — verbal authorizations are unenforceable in most state lien statutes (CA Bus. & Prof. Code §7164 requires written change orders on home-improvement contracts >$500). **The schedule is also a forecasting tool**: the GC uses it to time the Owner draw against subs' actual draws; the sub uses it for cash-flow planning and payroll. Mid-project re-baselining is normal — re-issue the schedule after each change order so the totals reconcile.

When to use it

  • Sub-to-GC payment schedule attachment to AIA A401 / consensus DOCS 750.
  • GC internal cash-flow planning vs. Owner draw schedule.
  • Sub-side cash-flow + payroll planning.
  • Re-baselining after change orders.
  • Prompt-pay statute documentation in late-payment disputes.

What to include

  • Project + parties + trade / scope + subcontract date + value.
  • Retainage % + release conditions.
  • Payment terms (net X, pay-when-paid, pay-if-paid w/ state-enforceability note).
  • Milestones — phase, deliverable, amount, target date, status.
  • Lien-waiver requirement (conditional + unconditional).
  • Change-order policy.
  • State-specific prompt-pay reference.
  • Signatures.

Frequently asked

Pay-when-paid is a TIMING clause: the sub gets paid AFTER the GC gets paid, but if the Owner never pays, the sub is still owed and can ultimately collect (or lien). Pay-if-paid shifts the Owner-credit risk to the sub: if the Owner never pays, the sub never gets paid. Pay-if-paid is unenforceable in NY (Lien Law §34), NC, CA public projects, and restricted in WI / IL / SC. Read the contract language carefully — courts construe ambiguity against the GC (the drafter).
⚠ Legal disclaimer. This payment schedule is a contract attachment and supplement; it does not override the underlying subcontract terms. Pay-when-paid vs. pay-if-paid enforceability + retainage limits + prompt-payment windows are STATE-SPECIFIC; consult a construction attorney for your jurisdiction. State-statutory lien-waiver forms (where they exist) must be used verbatim or the waiver may be unenforceable.
Jurisdiction: United States — state prompt-payment acts for private + public construction (CA Bus. & Prof. Code §§7108.5, 8800; Tex. Prop. Code §§28.001-28.010; Fla. Stat. §§715.12, 218.735; NY Gen. Bus. §§756-758; PA 73 P.S. §§501-516); pay-when-paid + pay-if-paid clause enforceability varies by state; AIA A401 §11 + A201 §9.6 payment provisions; UCC Article 2 for materials.
Last reviewed: 2026-05
Reviewed by ScoutMyTool — consult a licensed attorney for binding use.