Construction Daily Report

Daily jobsite log — date, weather, crew + labor hours, work completed by trade, materials + deliveries, equipment, visitors, safety + quality issues, photos referenced. Contemporaneous evidence for schedule + claim + payment disputes.

Customise

Live preview

CONSTRUCTION DAILY REPORT

═══════════════════════════════════════════════════════════════════════════

Project:           Maple Ridge Townhomes — Phase 2
Address:           1842 Maple Ridge Lane, Hillsboro, OR 97124
Report date:       May 28, 2026
Reported by:       Reilly Park · Site Superintendent
Work hours:        06:30 - 16:30 (10 h with 30 min lunch + 2x 15 min breaks)

WEATHER
  AM: 52°F · clear · wind 5 mph WSW · humidity 62% · ground dry
  PM: 68°F · partly cloudy · wind 10 mph WSW · brief sprinkle 14:20-14:35 · ground dried by 15:00

═══════════════════════════════════════════════════════════════════════════

CREW + LABOR HOURS

   Trade            | Crew                   | Hours
   -----------------|------------------------|------
   Framing          | 6 carpenters           |    60 h
   Electrical       | 2 electricians         |    18 h
   Plumbing         | 2 plumbers             |    16 h
   HVAC             | 1 mechanic             |     8 h
   Sitework         | 1 operator             |     9 h
   Supervision      | 1 super + 1 foreman    |    19 h
   -----------------|------------------------|------
   TOTAL            |                        |   130 h

═══════════════════════════════════════════════════════════════════════════

WORK COMPLETED  (by trade)
FRAMING: Completed roof truss installation on units 6-8 (24 trusses, all braced + sheathed); 90% of exterior wall sheathing on Unit 9 (south + east walls remaining).
ELECTRICAL: Rough-in of Unit 6 (devices boxed + home-runs to panel pulled); GFCI testing at Unit 5 panel.
PLUMBING: DWV stack rough-in on Unit 7 second floor; pressure-test of Unit 5 supply lines passed (40 psi held 30 min, no drop).
HVAC: Furnace + ductwork rough-in for Unit 5.
SITEWORK: Final grading at units 5-6 driveways; sod prep at Unit 5 front yard.

MATERIALS + DELIVERIES
07:45 — Truss delivery: 24 roof trusses for units 6-8 (Western Roof Truss PO #WRT-2026-1148; crane unload; verified against ship list, no damage).
10:30 — Lumber delivery: 84 sheets 7/16" OSB wall sheathing + 2,400 bf 2x6 framing (84 Lumber order 26-77144; tarped at storage area).
13:15 — Electrical: 1 PV-ready 200A main panel + 50 lbs 12-gauge Romex (Platt Electric Supply PO #PES-2026-04887; locked in Unit 5 garage).
14:00 — Plumbing: PEX pipe + manifold for Unit 7 (Ferguson order 2026-552). NOTE: 1 box of 1/2" fittings was short-count (12 of expected 24); credit memo issued by supplier.

EQUIPMENT ON SITE
Kubota mini-excavator (rental — sitework). Skid steer (owned — material moves). Bobcat T-770 forklift (owned — material handling). 60-ft articulating boom lift (rental — Sunbelt — for truss bracing). Generator 25 kW for temp power.

VISITORS + INSPECTIONS
08:15 — Project Architect (Casey Lim, Studio North) for walk of unit 5 framing alignment. No findings.
10:00 — County Building Inspector Eric Wong for Unit 5 rough-in inspection — APPROVED.
13:30 — Owner rep (Jordan Taylor) for weekly walk + finish-selection confirmation on Unit 7.
OSHA / state safety inspector: none today.

═══════════════════════════════════════════════════════════════════════════

SAFETY  (incidents + observations + toolbox-talks)
No recordable injuries. No near-misses.
07:00 toolbox-talk: fall protection on roof work (10 min). All crew signed in.
Mid-day observation: subcontractor electrician used non-GFCI extension cord; replaced + verbal coaching by safety officer.
PPE compliance 100%.

QUALITY  (rework, RFIs, non-conformances)
RFI #047: window-flashing detail at Unit 7 master bath — submitted to Architect for clarification (response expected within 48 h; no current schedule impact).
Rework: 2 sheets of OSB on Unit 6 had wrong cut; replaced from delivery stock. No impact to schedule.
Open RFIs total: 3 (#047 active, #044 + #045 awaiting response).

SCHEDULE STATUS + DELAYS
Schedule status: ON TRACK against current baseline. Critical path = Unit 7 dry-in (target 2026-06-04). Today's production met or exceeded planned (truss install +1 day favorable). No delays today.

PHOTOS
23 photos uploaded to project Procore — folder /Daily/2026-05-28/. Captioned: truss delivery (3), unit 6 framing progress (8), unit 7 plumbing rough-in (5), Architect walk (3), inspection sign-off (2), delivery damage check (2).

═══════════════════════════════════════════════════════════════════════════

SIGNATURE

Reporting party: _________________________     Date: _____________
                 Reilly Park · Site Superintendent

About this template

A construction daily report is the most-litigated document on a jobsite — courts call it "contemporaneous evidence" and it is the difference between winning and losing a schedule, delay, back-charge, or productivity claim. **Five sections do the legal work**: (1) **Weather** — drives weather-day claims (most contracts allow a non-compensable time extension for X days of >Y rain or temperature outside Z range; the daily report is the trigger), (2) **Crew + hours** — drives lost-productivity claims and dilution arguments under the Modified Total Cost or Measured-Mile methodologies, (3) **Work completed** — the basis for payment applications + earned-value, (4) **Visitors + inspections** — chain-of-evidence for code-compliance defenses and Architect direction, (5) **Schedule status + delays** — the contemporaneous record that defeats a Total-Cost claim if it shows no actual disruption occurred. **AIA A201 §15.1.3** requires written notice of claims within 21 days; the daily report is often the first evidence of when an issue arose. **OSHA citations** routinely use daily reports as evidence of training, toolbox-talks, and observation of unsafe acts. **Pay applications** that don't reconcile with daily-reported work-completed are routinely rejected. **Best practice**: complete the report at end-of-shift before leaving site (memory fades fast); photo + caption every material delivery, every inspection, and every disputable condition; capture sub-tier visitor sign-in and exit times; record the cause + duration of any pause >15 min (rain, material wait, inspection delay, equipment breakdown). **Common mistakes**: (a) over-aggregating crew counts loses Modified Total Cost causal-link evidence; (b) leaving weather as "normal" defeats the weather-day claim; (c) skipping the safety section creates an OSHA evidentiary gap; (d) reporting "no delays" when delays actually occurred is an admission against interest later. The daily report is also the **bridge to the weekly Owner meeting** — the seven daily reports become the foundation of the weekly executive summary.

When to use it

  • Every work day on every active jobsite (no exceptions — gaps are evidentiary problems).
  • Schedule, delay, productivity, and back-charge claim documentation.
  • AIA A201 §15.1 written-notice trigger evidence.
  • OSHA citation defense (training, observation, PPE compliance).
  • Pay-application reconciliation.
  • Owner / Architect weekly meeting source data.

What to include

  • Project + date + reporting party.
  • Weather AM + PM (with material precipitation / temp / wind).
  • Crew + labor hours by trade (counts + hours).
  • Work completed narrative by trade.
  • Materials + deliveries (PO #, time, condition).
  • Equipment on site (owned + rented).
  • Visitors + inspections (Architect, Owner, code official, OSHA).
  • Safety — incidents, near-misses, toolbox-talks, PPE compliance.
  • Quality — RFIs, non-conformances, rework.
  • Schedule status + delays (with cause + duration).
  • Photos referenced (count + filing location).
  • Signature.

Frequently asked

Contractually 3-7 years depending on the contract; statutory 4-6 years per most states' contract statute of limitations; OSHA 5 years for OSHA-300 referenced items. Practical retention: keep until project warranty + statute of repose has run (10-12 years in most states). Cloud-store with dated metadata; the daily report is the most-requested document in construction litigation.
⚠ Legal disclaimer. This daily report is operational + evidentiary. It is not legal advice and does not substitute for contract-specific notice provisions (e.g. AIA A201 §15.1, ConsensusDocs equivalents). State statutes of limitations + repose vary; consult counsel for retention requirements. The Contractor remains responsible for compliance with all applicable OSHA + state-plan safety standards regardless of the report content.
Jurisdiction: United States — operational record. Often referenced as contemporaneous evidence in delay/disruption claims (Eichleay damages, total-cost claims), back-charge disputes, and OSHA citations. AIA A201 §3.10 + §15.1 use the term "daily construction report" implicitly via the Contractor schedule + claim notice requirements.
Last reviewed: 2026-05
Reviewed by the ScoutMyTool editorial team, Founder — consult a licensed attorney for binding use.

Related templates

More tools you might like

Hand-picked tools that pair well with this one — same audience, same intent.

Contractor Punch List
Docs

Construction close-out punch list — track each defect / incomplete item by location + trade + status + completion date + sign-off. Used at substantial-completion walk-through to clear items before final payment + retainage release.

Job-Site Safety Inspection
Docs

Job-site safety walk-around inspection — PPE, fall protection, electrical, signage, housekeeping, hazard observations, corrective actions. Aligns with OSHA 29 CFR Part 1926 construction standards.

Residential Construction Contract
Docs

Contract between homeowner and contractor for residential construction or major renovation - scope, payment, change orders.

Construction Change Order
Docs

Written change order modifying an existing construction contract - scope, cost, time impact.

Daycare Daily Report
Docs

A daycare daily report for parents — meals and how much was eaten, naps, diaper/bathroom log, activities, mood, supplies needed, and notes from the caregiver.

Beach Lifeguard Daily Log
Docs

A daily beach lifeguard log — tower / shift details, beach conditions (flag, surf, water temp, UV), hourly attendance estimate, rescues and assists, medical calls, equipment status, and supervisor sign-off.

Daily Standup Notes Template
Docs

Daily standup (daily scrum) notes — per-person Yesterday / Today / Blockers, with date, team, attendees, and a team-blockers / parking-lot section.

Mortgage Payoff Schedule (PDF Report)
PDF

Generate a printable amortisation / payoff schedule PDF — enter the balance, rate, and payment, get a month-by-month payoff table.